Documents, Including Messages and Other Communications, Part 31904 |
Des de l'interior del llibre
Resultats 1 - 5 de 50.
Pàgina 87
... dredging the M. & . E canal between Cincinnati and Dayton . For permanent improvement on walls in Cincinnati , Ohio .. For improvement of Summit county reservoir , etc. For repairs and permanent improvement upon the embankment on Six ...
... dredging the M. & . E canal between Cincinnati and Dayton . For permanent improvement on walls in Cincinnati , Ohio .. For improvement of Summit county reservoir , etc. For repairs and permanent improvement upon the embankment on Six ...
Pàgina 91
... Dredging M. & E. Canal . • Jno . O'Connor , Dredging M. & E. Canal .. Chas . Cooper , improvement Miami and Mad River dams . Chas . Cooper , building canal walls in Cincinnati . $ 23,132 00 17,691 00 31,250 84 103 16 $ 4,740 58 3,596 12 ...
... Dredging M. & E. Canal . • Jno . O'Connor , Dredging M. & E. Canal .. Chas . Cooper , improvement Miami and Mad River dams . Chas . Cooper , building canal walls in Cincinnati . $ 23,132 00 17,691 00 31,250 84 103 16 $ 4,740 58 3,596 12 ...
Pàgina 144
... dredging at 15 cents per cubic yard To paving canal banks under bridges and where canal is necessarily confined to forty feet width at surface of water at the following places . Five mile level , Pinery level , Akron locks , Summit ...
... dredging at 15 cents per cubic yard To paving canal banks under bridges and where canal is necessarily confined to forty feet width at surface of water at the following places . Five mile level , Pinery level , Akron locks , Summit ...
Pàgina 145
... dredging at 20 cents per cubic yard ..... To ten per cent . for engineering , superintendence , and contingencies Total cost of improvement 136,000 00 18,777 31 $ 206,550 39 . Division No. 2 from Dayton to New Bremen , Including BOARD ...
... dredging at 20 cents per cubic yard ..... To ten per cent . for engineering , superintendence , and contingencies Total cost of improvement 136,000 00 18,777 31 $ 206,550 39 . Division No. 2 from Dayton to New Bremen , Including BOARD ...
Pàgina 146
... dredging at 20 cents per yd ...... .. To repairing reservoirs , as follows : Lewistown Reservoir , material and labor Loramie Reservoir , material and labor Loramie Waste Weir , material and labor Loramie Reservoir , waste gates To ...
... dredging at 20 cents per yd ...... .. To repairing reservoirs , as follows : Lewistown Reservoir , material and labor Loramie Reservoir , material and labor Loramie Waste Weir , material and labor Loramie Reservoir , waste gates To ...
Altres edicions - Mostra-ho tot
Frases i termes més freqüents
26 days A. W. Jackson ABSTRACT OF MONEY Account acres Amount appropriation April aqueduct Auditor Blacksmith Board of Public brick erected bushels capita cells Chas Children's Home Cincinnati Cleveland Coal Columbus Mill condition construction Contingent expenses Coshocton cost COUNTY culvert current expenses days as carpenter days as laborer Dayton dozen dredge electric employes ending November 15 epileptic Erie Canal Farm contains feeder Feeding feet floor Fordyce Freight H. H. Shirer Hardware heated by steam Hocking hospital improvement Infirmary inmates insane institution jail John land laundry LICKING COUNTY lock Lockland LOGAN COUNTY Member's traveling expenses Miami and Erie Muskingum National Biscuit Co November 15 Number Ohio Canal Ohio State Reformatory paid Pay roll Payroll Piqua pounds Reservoir Sheriff steam and lighted Steam heat Summit superintendent since March supplies Supt Telephone Thomas N Toledo Total for month two-story brick walls water closets yards